The CITB's Construction Workforce Outlook 2026 to 2030 is not a prediction about the industry in general. Read at regional and occupational level, it is a list of the trades and roles that will be hardest to put on your next programme, and it names London and the South East specifically.
This piece treats the published figures as a resourcing risk document rather than a policy story, and sets out what that means for programme planning, procurement and the case for bringing a contractor in earlier.
What does the CITB's Construction Workforce Outlook 2026 to 2030 forecast?
The Construction Industry Training Board's annual Outlook is produced with Oxford Economics and sets out expected construction demand over the next five years and the implications for the construction workforce. The headline for contractors is a persistent gap between the people the industry will need and the people likely to be available.
At UK level, an average of 41,200 extra workers will be needed each year between 2026 and 2030, equivalent to 1.6% of the 2025 workforce, or around 206,000 additional workers over the five year period. The workforce itself is forecast to reach around 2.68 million by 2030, up from 2,606,380 in 2025, but that is a net figure. It assumes continuous replacement of leavers at the same time as growth.
CITB's own framing is cautious rather than alarmist. The Outlook shows growth is expected to return to the industry over the medium-term, but that it continues to face ongoing pressures in recruiting and retaining the workforce it needs, with the short-term picture for construction challenging, with uncertainty and cost pressures affecting activity. The interactive tool puts a number on the short-term dip: UK output growth of -0.2% in 2026, improving to 1.8% in 2027, peaking at 2.8% in 2028, then easing to 2.3% in 2029 and 2.1% in 2030. CITB's chief executive, Tim Balcon, described the report as offering “the evidence needed to guide workforce and skills planning in a period of significant opportunity and challenge”.
That combination, a soft 2026 followed by a recovery the workforce is not yet sized for, is exactly the pattern that catches programmes out. Resourcing looks manageable at tender stage, when activity is subdued, and becomes the live constraint once work actually arrives.
Why don't London and the South East match the national average?
The England report breaks the national figure down by region, and the two regions PV Consulting works across sit either side of the UK average, for different reasons.
Greater London needs more extra workers than the England average implies. The forecast shows that recruitment would have to increase by the equivalent of 6,780 extra workers per year, equivalent to approximately 1.8% of the 2025 workforce, slightly higher than the UK figure of 1.6%. The region's workforce is also still recovering lost ground. The 2024 workforce of 387,590 decreased slightly to 368,120 in 2025, and is forecast to increase steadily to reach 382,900 by 2030, which means London's 2030 workforce is still forecast to sit below its 2024 level even as demand for extra workers remains above the national rate.
The South East's pressure shows up differently. Recruitment would have to increase by the equivalent of 5,780 extra workers per year, approximately 1.5% of the 2025 workforce, slightly lower than the UK figure of 1.6%, and output growth of 1.6% a year is in line with the UK rate. But the region's workforce is forecast to grow more slowly than demand would suggest: an annual average increase of 0.5% in the construction workforce, which is slightly lower than the UK figure of 0.6%. A region with over half its output in repair and maintenance work, as the South East has, still needs to find the people, even where new build volumes are more modest.
The practical read for a contractor working across both regions is that you cannot apply one resourcing assumption. London's constraint is volume and recovery lag, the South East's is a workforce growing slower than the demand curve.
Which trades will be hardest to resource on site?
CITB's occupational breakdown is the part most useful for a programme, because it names the roles rather than just the headline number.
In London, the demand for extra workers is higher for occupations such as steel erectors and metal workers (2.5% of 2025 workforce), other professionals and technical staff working in construction (2.4%), and bricklayers and masons (2.3%). In the South East, demand is higher for occupations such as bricklayers and masons (1.9% of 2025 workforce), construction trades supervisors (1.9%), and architects (1.8%). Across England as a whole, the strongest proportional demand sits with civil engineers (2.3%), architects (2.0%), surveyors (2.0%) and construction trades supervisors (2.0%).
Two things follow from that list. First, it is not a general labourer shortage, it is concentrated in specific trades and in professional and technical roles, including the supervisory and engineering functions that hold a programme together. Second, the supply chain delivering those trades is thin by structure as well as by headcount: over 90% of England's 166,905 active construction employers were micro businesses with under 10 employees, and only 1,915, 1.1% of the total, had more than 50 employees. A shortage concentrated in a handful of trades, delivered mostly by small firms with limited capacity to absorb a second contract, is a sequencing risk, not just a cost risk.
How should resourcing risk show up in the programme itself?
Most programmes still treat labour as infinitely elastic, a resource that stretches to meet whatever sequence the planner draws. The Outlook gives a basis for not doing that.
- Name the trades on the critical path. Where steel erection, bricklaying or civil engineering design review sit on or near the critical path, flag them specifically rather than relying on a general float allowance.
- Add float around the tightest packages, not evenly across the programme. A flat 10% contingency does nothing for a sequence that depends on one steel erection gang with no realistic second source.
- Revisit float assumptions as the 2026 to 2027 recovery lands. CITB's own forecast shows output accelerating from 2027, which is also when the workforce is expected to start growing again rather than contracting. A programme priced in a soft market will not automatically hold once activity picks up.
- Treat design and review capacity as a resourced activity, not a free good. Civil engineers and supervisory roles appear among the tightest occupations nationally. If your structural engineering and project management support is assumed rather than booked, that is a resourcing risk too.
What should change in procurement and prequalification?
If the labour market is tight in named trades and dominated by small firms, procurement needs to ask different questions than it did when supply was looser.
Ask bidders for their actual resourcing plan for the specific trades the Outlook flags as tight in your region, not a generic method statement. Ask how many live contracts their proposed steel erection or bricklaying subcontractor is currently resourcing elsewhere, and what happens if that subcontractor is awarded a second large contract in the same window. Where a single specialist package carries disproportionate programme risk, consider splitting it or securing it earlier than the rest of the package strategy would normally dictate.
This is also a reason to revisit design review and temporary works procurement timing. If independent design checks and temporary works design are left until a subcontractor is appointed, and that appointment slips because the trade is scarce, the review work slips with it, even though it did not need to.
Can early contractor involvement actually de-risk resourcing?
Early contractor involvement is usually sold on buildability and cost certainty. Against a workforce forecast like this one, it has a resourcing argument too.
Bringing the contractor, and the trades most exposed to the Outlook's figures, into the conversation during design rather than after tender means sequencing decisions can be tested against realistic trade availability, not an assumed supply chain. It also means package boundaries can be drawn around where capacity actually sits, rather than around a design logic that ignores it. None of this removes a national shortfall of 41,200 workers a year. What it does is move the point at which the shortfall is discovered from the middle of the programme, where it becomes a delay, to the pre-construction stage, where it is still a decision. Our note on pre-construction structural review for contractors covers the same logic applied to buildability and design information, and the two exercises sit well together.
Where does independent technical support reduce exposure to the skills gap?
The Outlook's professional and technical figures are a reminder that the shortage is not confined to site trades. Civil engineers, architects and surveyors all show above-average proportional demand nationally, and construction trades supervisors are tight in both London and the South East. That is the layer of the workforce that produces temporary works designs, checks permanent designs for buildability, and supervises the interface between the two.
For a contractor, the practical response is to treat independent engineering capacity, temporary works design, design checks and pre-construction review, as something to secure against a programme date, not something to source reactively when an internal resource is unavailable. A Chartered Engineer working directly on a scheme does not depend on the same recruitment pipeline the Outlook describes for in-house supervisory and technical staff, which is one reason contractors bring in that capacity specifically for periods when their own resourcing is under pressure.
If the CITB figures for your region or trade mix are changing how you would sequence or procure an upcoming scheme, our project management and technical support service for contractors covers exactly that transition from a tender assumption to a resourced plan. You can discuss a specific programme through our contact page or by phone on 07715 541143.