RAAC in Commercial Buildings: A Guide for Contractors and Developers

By Pasquale Vacirca, CEng MICE

Send an enquiry

Or call 07715 541143

01 In short

The answer first

RAAC is no longer a schools-only issue. Here is how contractors and developers should identify, assess and remediate it during refurbishment or acquisition due diligence.

RAAC stopped being a schools-only story some time ago. The Institution of Structural Engineers updated its RAAC statement as recently as July 2026, and RICS refreshed its RAAC FAQ page in February 2026, both still being issued because the material keeps turning up in courts, theatres, sports halls, offices, warehouses and now residential stock well beyond the 2023 crisis. For anyone refurbishing or acquiring a building from the mid-1950s to mid-1990s, RAAC is a due diligence question with a defined process, not a guess.

This article sets out what RAAC is, how the Identification, Assessment, Solutions process actually works, and where a Chartered or Incorporated Structural Engineer has to be involved rather than an estates manager working through a checklist.

Why Contractors and Developers Are Seeing RAAC Again

The 2023 school closures gave RAAC its public profile, but the material was never confined to education. RICS notes that RAAC is believed to be more common in schools, hospitals and public buildings, but has also been discovered in courts, theatres, sports halls, public toilets and a range of non-domestic buildings, with isolated examples in domestic properties, notably in parts of Scotland.

The point is sharpened by one detail in the IStructE's own statement. When the Department for Education asked the Institution to review its guidance against three reported RAAC failures in 2023, one of them was the failure of a roof panel in end bearing or shear in a commercial setting, where the panel fall had been arrested by machinery below. That single case is the clearest evidence that this was never only an education estate problem, and the Institution's study group concluded its existing guidance already covered all three failures without needing to be strengthened.

For a main contractor taking on a refurbishment, or a developer running acquisition due diligence on a 1960s office block, retail unit or industrial shed, the practical question is not whether RAAC is a historic issue. It is whether the building in front of you falls inside the affected period and construction type, and if so, what the process for dealing with it actually requires.

What RAAC Is, and Where It Hides

RAAC is a highly aerated, lightweight form of reinforced concrete, built without aggregate, used mainly to form roof planks but also in some floor and wall panel construction from the mid-1950s to the mid-1990s, with evidence of use continuing in a limited number of buildings into the 1990s and 2000s. Because it has no aggregate, it behaves differently from traditional reinforced concrete, and the durability concerns attached to it do not extend to conventional concrete structures elsewhere in the same building.

The practical identification markers, as set out by RICS, are straightforward to check against:

  • The age bracket. Buildings, or extensions, built before the mid-1950s or after the mid-1990s are unlikely to be affected.
  • Local authority records of similar buildings in the area with confirmed RAAC.
  • Construction records, bearing in mind RAAC may not be explicitly named even where it was used.
  • Product names. RICS lists Siporex, Durox, Celcon, Hebel and Ytong as indicators of RAAC.

This stage, checking age, records and product names, does not require a RAAC specialist. The IStructE's guidance page is explicit that identification can be undertaken by an experienced estate or maintenance manager or building owner, and that the person doing it does not need to be a RAAC expert to establish whether the building has it. Where the construction type is uncertain, both bodies converge on the same answer: get a professional involved before drawing conclusions about condition.

Identification, Assessment, Solutions: The Process in Practice

The IStructE frames the whole management route in three steps, and the boundary between them is where competence requirements change.

Identification establishes whether RAAC is present at all. As above, this can be done in-house, or by a structural engineer or surveyor if there is doubt about the construction type.

Assessment is different in kind. Once RAAC is confirmed, the IStructE is clear that the building needs to be assessed to understand what risk exists and whether immediate temporary remedial work is required, and that this is where Chartered and Incorporated Members become competent to act. Assessment is not a visual check. RICS warns that defects can be difficult to identify given the nature of the material, and that building owners should not attempt to assess the condition of known RAAC planks themselves.

Solutions follows the assessment. The IStructE confirms that competent structural engineers evaluate all the available information, including a detailed site inspection, and propose remedial works, which may range from monitoring through to propping, strengthening, or removal and replacement of panels.

The reason this distinction matters on a live project is procurement timing. Identification can happen during a desktop acquisition review or a pre-contract survey without delaying anything. Assessment and solutions cannot be compressed into the same timetable, because they depend on intrusive inspection of bearings and reinforcement condition that a desktop exercise cannot replace.

Why a Chartered or Incorporated Structural Engineer, Specifically

Both bodies name the qualification deliberately rather than using "a structural engineer" loosely. RICS's advice is to use a suitably qualified professional, such as an RICS chartered building surveyor or chartered structural engineer, and it flags reports of unqualified traders cold calling households offering RAAC surveys, with the advice to always use a member of a regulated professional body such as RICS or IStructE. The IStructE's own position ties this to its Code of Conduct, under which members must undertake only tasks they are competent for, operate within their area of competence, and maintain that competence through continuing professional development including staying current on RAAC guidance.

For a contractor, this has a direct commercial consequence. If a survey has been carried out by someone outside this bracket, it is not evidence you can safely price or programme against, and a client's due diligence pack is only as reliable as the credentials of whoever wrote it. Our structural engineering service and our note on independent design checks cover the same principle in a different context: a second opinion from a competent, appropriately qualified engineer is cheaper than acting on an assessment you cannot stand behind.

What Remediation Actually Involves Once RAAC Is Confirmed

RICS is candid that there is no single answer to cost or duration, because both depend on the size of the building, its location, and whether temporary works such as a temporary roof are required during the works. Removing a RAAC flat roof, for instance, can also become an opportunity to redesign the roof build-up, which brings in planning and Building Regulations considerations rather than a like-for-like replacement.

Two practical points carry across from the education sector guidance into commercial and residential refurbishment:

  • Risk is use-dependent. RICS frames this in terms of a classroom being higher risk than a storeroom or plant room beneath the same roof type. The same logic applies to an occupied office floor against a service riser or plant deck.
  • Flat roofs with suspected RAAC should not be walked on. RICS advises that a risk assessment using techniques such as camera poles or drones is required before a roof is remediated, and that heavy equipment should never be placed on a flat roof in this condition.

Where temporary propping is the interim measure, that propping is itself a structure requiring a load path to a foundation, which is exactly the kind of item that belongs in a pre-construction structural review rather than being discovered once scaffolding is already up. Our temporary works design service covers this directly.

Does RAAC Change the Deal? Valuation and Due Diligence

For a developer running acquisition due diligence, the honest answer from RICS is that it depends on scale. RICS explains that identification of RAAC leads to further investigation and a management or remediation scheme, and where that scheme is fairly simple, such as permanent propping, it is likely such modest costs will not affect the value of the property. A much larger remediation scheme, such as removing a large RAAC flat roof, is more likely to affect value, because the remediation cost will be taken into account by a valuer.

That distinction is only meaningful once assessment has actually happened. A desktop note that a building "may contain RAAC" is not a valuation input; a structural engineer's assessment of bearing condition and extent is. This is squarely feasibility and pre-construction territory, and our feasibility and pre-construction service and property consultancy service exist to turn a suspicion into a number a transaction can actually use.

Mixed Tenure and Residential Stock: The Scotland Precedent

The clearest evidence that RAAC has moved beyond the 2023 schools crisis is in Scottish social and mixed tenure housing. RICS reports that the Scottish Housing Regulator's mid-2025 data confirms 17 social landlords have identified RAAC in their housing stock, affecting around 2,200 to 2,450 homes, roughly 0.4% of Scotland's social housing, with Aberdeen City, Dundee City, City of Edinburgh, Clackmannanshire, North Lanarkshire, South Lanarkshire and West Lothian councils among the most affected, and all social landlords having completed initial investigations with management or remediation plans in place.

The harder problem, as RICS describes it, sits in mixed tenure estates, where council tenants have often been rehoused while private homeowners remain in properties that may be unsellable, unmortgageable and uninsurable, a situation RICS identifies as particularly acute in Aberdeen's Balnagask and Torry areas, Dundee, and Tillicoultry, with some neighbourhoods partially or fully vacated. In January 2026, the IStructE published two-part guidance specifically on RAAC in the roofs of domestic properties in Scotland, which RICS notes may also be useful when considering other building types or regions even though it was written for Scottish residential roofs.

For developers and housing providers in London and the South East, this is not a direct precedent, since RAAC incidence has so far been concentrated differently by geography and tenure. It is, however, a working model for what happens when RAAC is confirmed in occupied mixed tenure stock, and a reason to treat any RAAC finding in residential refurbishment as a tenure and insurance question as much as a structural one from the outset.

What This Means for Your Next Refurbishment or Acquisition

If you are pricing a refurbishment or running due diligence on stock from the affected period, the sequence that avoids both delay and liability is the one both institutions describe: identify against age, records and product names first, bring in a Chartered or Incorporated Structural Engineer the moment RAAC is suspected or confirmed, and keep assessment and asbestos investigation on the same timeline rather than treating one as a follow-on from the other.

Where that assessment turns into propping, strengthening or a roof replacement, the same engineer carrying out the assessment is best placed to take the solution through design, because the bearing and loading data from the assessment feeds directly into the remedial design. Our structural engineering team and contractor support services cover London and the South East, and if you have RAAC suspected or confirmed on a current or upcoming project, contact us on 07715 541143 to talk through the assessment and remediation route before it becomes a programme problem.

02 Questions

Frequently asked questions

What is RAAC and when was it used in the UK?

RAAC is a lightweight, reinforced form of aerated concrete used mainly for roof planks, and sometimes floor and wall panels, from the mid-1950s to the mid-1990s, with isolated later use. It is most associated with schools, hospitals and public buildings, but appears across commercial stock too.

Can we identify RAAC ourselves during a survey or acquisition?

Initial identification against the age bracket, records and product names such as Siporex or Durox can be done by an experienced estate or maintenance manager. If you are unsure, or RAAC is confirmed, a structural engineer or surveyor should take over before any condition judgement is made.

Who has to assess RAAC once it is found?

A Chartered or Incorporated Structural Engineer. Identification does not require a RAAC specialist, but assessing risk, bearing condition and proposing remedial solutions does, and that person must only accept work within their area of competence under their Institution's Code of Conduct.

Does finding RAAC affect a property's value?

Not automatically. Modest remediation such as permanent propping is unlikely to affect value. A large scheme, such as removing an extensive RAAC roof, is more likely to be reflected by a valuer because the remediation cost becomes a factor a surveyor has to account for.

Is RAAC linked to asbestos?

No, there is no compositional link. The concern is purely durability and structural performance. However, RAAC dates from an era when asbestos was legal, so buildings with RAAC often need asbestos identification and testing before remediation work starts in that location.

What should a developer do if RAAC is suspected during due diligence?

Treat it as a structural question, not a commercial footnote. Commission inspection and risk assessment before exchange where possible, avoid walking or loading suspect flat roofs, and get a structural engineer's view on propping, access and remediation scope before pricing the works or the deal.